Skip to main content
Sunday, October 18, 2026
Home
Omaha Daily Record
  • Login
  • Home
  • Subscribe
  • Calendar
    • Real Estate
    • Small Business
    • Non-Profit
    • Political
    • Legal
  • Podcasts
    • Real Estate
    • Small Business
    • Non-Profit
    • Political
    • Legal
  • Profiles
    • Real Estate
    • Non-Profit
    • Political
    • Legal
    • Small Business
  • E-Edition
    • Current Issue
    • Archives
  • Real Estate News
    • Market Trends
  • Business News
  • Non-Profit News
  • Political News
  • Legal News
  • Editorial
    • Empower You
    • The Jerk Of All Trades
    • Tom Becka
  • Other News
  • Advertise
    • Place a Legal Notice
    • Place a Print Ad
    • Place a Classified Ad
    • Place an Online Ad
    • Place Sponsored Content
  • Available For Hire
    • Real Estate
      • Contractors
      • Clerical
    • Legal
      • Paralegal
      • Clerical
  • About
    • Our History
    • Our Office
    • Our Staff
    • Contact Us
  • Public Notices
    • State of Nebraska
    • City of Bennington
    • City of Gretna
    • City of Valley
    • Douglas County West Community Schools
    • Gretna Public Schools
    • Metro Transit Authority
    • Omaha Airport Authority
    • Omaha Housing Authority
    • Plattsmouth Community Schools
    • Springfield Platteview Community Schools
    • City of Omaha
    • Douglas County
      • Tax Delinquency 2026
    • City/County Notice of Bids
    • City of Ralston
    • Omaha Public Schools
    • Millard Public Schools
    • Ralston Public Schools
    • Westside Community Schools
    • Bennington Public Schools
    • Learning Community
    • MAPA
    • MECA
    • Douglas-Sarpy Extension Board
    • Village of Boys Town
    • Village of Waterloo
    • Sarpy County
      • Tax Delinquency 2026
    • City of Bellevue
  • Public Records
    • Building Permits
    • Mechanical Permits
    • Wreck Permits
    • Electrical Permits
    • Plumbing Permits
  • Real Estate Leads
    • Notice of Default
    • Deeds
    • Active Property Sales
    • Active Probates

You are here

Home » A Build America, Buy America Law Is Causing Construction Delays Amid The US Housing Crisis

A Build America, Buy America Law Is Causing Construction Delays Amid The US Housing Crisis

Published by maggie@omahadai... on Thu, 04/02/2026 - 12:00am
By 
Charlotte Kramon
The Associated Press

It has a catchy name — Build America, Buy America — and the lauded goal of bringing manufacturing jobs back to the United States.

But the law has spurred a bottleneck for affordable housing.

Nearly everything from HVACs and lighting to sink hooks and ceiling fans in affordable housing projects that get federal dollars must be produced in the United States. But, developers say, numerous products do not, as they have long been imported from overseas markets with cheaper labor costs.

Although builders can apply for waivers, the process has been at a near standstill as the Department of Housing and Urban Development, which has had its staff slashed by the Trump administration, has only greenlit a handful of projects.

The waiver process has caused construction delays and hundreds of thousands of dollars in extra costs as the country faces an affordable housing crisis.

“They need to be treating this like the fire that it is,” said Tyler Norod, president of Westbrook Development Corporation, which builds affordable housing in Maine.

“We’ve sort of resigned ourselves that we’re just gonna build less units across the entire country during a housing crisis.”

Facing A Standstill

Diana Lene has been on affordable housing waitlists for the past five years. The 75-year-old loves living close to her daughter and grandchildren in Fargo, North Dakota, but her apartment is too expensive on her Social Security income.

“It's just maxing my budget down to pennies,” she said. To save money, she avoids driving often and buys food on sale.

“I’m just trying to keep a roof over my head, but it’s getting more and more difficult,” Lene said. “I don’t like to live in fear, and yet sometimes it jumps in there.”

Lene is on a waitlist for one of nonprofit developer Beyond Shelter’s apartments. CEO Dan Madler is building a 36-unit building for people like Lene, but he had to postpone lumber orders to verify they comply with the law and can’t find ceiling fans made in America. He doesn’t know when HUD will approve a waiver.

U.S. President Joe Biden signed the Build America, Buy America Act as part of the Infrastructure Investment and Jobs Act in 2021, building on longstanding efforts to boost American manufacturing at a time when the U.S. economy was emerging from a pandemic-era recession. Known as BABA, it applies to infrastructure projects funded by federal agencies, not just affordable housing.

Denver developer Julie Hoebel says she has spent over $60,000 just on a consultant to comb through websites and call suppliers to try to find American-made materials, not to mention the additional labor costs involved.

But the waivers she submitted to HUD in November for around 125 materials in an 85-unit building haven't been approved.

“If they take much longer then we’ll come to a standstill,” she said.

A Cumbersome Process

HUD is taking at least six months to approve many waivers.

Even BABA advocates agree HUD must grant waivers more quickly and give the industry clearer instructions on how to prepare them, which they note other federal agencies are doing.

HUD did not address questions from The Associated Press about waiver approval delays developers say increase costs, as well as concerns about making the process more transparent. In a statement it said it's committed to “ensuring that federal spending supports America’s industrial base” while “closely monitoring how compliance with these policies impact costs for builders.”

Asked in January about whether the delays and cost increases mean affordable housing should be exempt from BABA rules, HUD Secretary Scott Turner said the agency was looking into the issue, but did not provide details. “We are looking at this ... with BABA as it pertains to HUD to provide flexibility to certain projects in certain places around our country,” Turner said, adding that HUD is committed to assuring developers get “the flexibility they need as it pertains to building.”

The law itself isn’t the problem, supporters say.

Unions representing the steel and manufacturing industries say taxpayer dollars should fund American-made materials and suppliers will adjust to meet demand for products that aren’t available.

“You’ve got a system in place that leans heavily on using imported materials to make a better profit,” said Scott Paul, president of the Alliance for American Manufacturing. “I don’t know if that serves the public good.”

Jennifer Schwartz, director of tax and housing advocacy at the National Council of State Housing Agencies, said there's no national data on how much BABA is increasing costs. But the waiver process is “failing,” she said, because requirements were put in place before assessment of domestic manufacturing capacity.

It won't be as challenging for suppliers to produce more raw materials in the U.S., but it will take time for manufactured products — such as appliances and elevators — to become available, said Kaitlyn Snyder, managing director of the National Housing and Rehabilitation Association, an affordable housing industry group.

“I don’t know that it economically, financially makes sense for people to be producing door hinges,” Snyder said. “We are an advanced country and we’ve outsourced a lot of that stuff.”

The housing bill that passed the Senate in March did not require HUD to address problems with implementing BABA.

“The process isn’t working for affordable housing,” said Jessie Handforth Kome, who spent nearly 40 years working at HUD until 2024. “People want to comply, but it’s unclear how to.”

Vermont-based Developer Jessica Neubelt estimates she spent an additional $150,000 just to verify iron and steel she used in a project was American-made. She’s just as frustrated over the hundreds of hours that takes, which, she said, could be spent on another project.

“I would like every member of Congress to sit in on a construction meeting,” Neubelt said. “The amount of detail that goes into figuring out if a specific thing is compliant or not is enormous.”

Debates Over Solutions

U.S. Rep. Mike Flood, a Nebraska Republican, has advocated to exempt some HUD funding from BABA.

“Owning a home is the American dream, but it’s out of reach in a very big way and anything that adds cost to that isn’t allowing hardworking Americans to achieve the dream,” Flood told the AP.

Roy Houseman, legislative director at United Steelworkers, said complaints about cost increases are overblown.

“A lot of developers seem to have tried to throw things in and make statutory changes to policies that have been in place for basically five years now instead of making a good-faith effort to really push HUD,” Houseman said.

Union leaders note the law offers some leeway.

Developers can get exemptions for an American-made product if it increases the project’s overall cost by more than 25%. A very small percentage of a project's total material cost is also exempt. But most developers say that percentage isn’t enough to cover all items not made in the U.S.

Some developers are looking for ways to avoid federal funds altogether. But that is challenging. Even though federal dollars often make up a small portion of funding for affordable housing projects, that sliver can make or break whether there's enough money to build them.

Kentucky developer Scott McReynolds says that instead of applying for a federal grant to build 20 to 30 affordable homes, he plans to build two four-unit projects, small enough so that they aren't subject to BABA.

American-made materials are especially hard to find near the rural areas McReynolds serves.

“It’s a nightmare,” he said.

 

Kramon is a corps member for The Associated Press/Report for America Statehouse News Initiative. Report for America is a nonprofit national service program that places journalists in local newsrooms to report on undercovered issues. This story was published originally by the Associated Press. Read the original article at: https://apnews.com/article/affordable-housing-construction-baba-hud-delays-4302744b3b5839268acaee92bf172eb9

Category:

  • Real Estate News

User login

  • Request new password

            

Latest Podcasts

  • Real Estate
  • Political
  • Political
  • Real Estate

Nebraska Landlord

Betches Sup - A Liberal News Commentary

Ruthless - A Conservative News Commentary

REIA Radio Show

Omaha Daily Record

The Daily Record
222 South 72nd Street, Suite 302
Omaha, Nebraska
68114
United States

Tele (402) 345-1303
Fax (402) 345-2351
 

The Daily Record
222 South 72nd Street, Suite 302 | Omaha, Nebraska 68114 | United States | Tele (402) 345-1303 | Fax (402) 345-2351 | Sitemap
Site Design, Programming & Development by Surf New Media